2008-2009 Priorities and Capital Expenditures
City of Bainbridge Georgia
2008 City Council Priority Issues
1. Paving projects should continue as rapidly as possible
2. Crime and Drugs-community and city responses.
3. Improved Public Information and Communication effort.
4. Beautification/litter control
5. Infrastructure issues including sewage upgrades, road, sidewalk improvement, bike lanes, and river connectivity plan
6. Continue to work toward "containing" gang/youth related activities from spreading/growing.
7. City Hall Renovation/Expansion
8. City plantings and beautification
9. Solid Waste Transfer Station.
10. Streetscape Phase Two
Priorities 2008-2009
Paving around shop
Resurfacing
Paving of dirt roads
Sidewalks
Continue GIS mapping of city utilities
Remodel Public Safety
Ladder truck
Sports complex
Inserta valve
Water Master Plan
Treatment Plant upgrades
Continuation of Sewer master plan
Automated meter reading system
Live scan finger print
Phase II Streetscape
Kiwecki Bldg./City Hall Complex
Connectivity Project
Purchase fork lifts (utilities, shop, purchasing)
Improve playgrounds
Upgrade & expand campground
Fire equipment needed for ISO reduction
Comprehensive Plan Update
Hire Human Resource Director
2008-2009 Proposed Capital Outlay
Division
Department Account/Item
Council & Appointments
City Manager
54.2201-Vehicle 27,000
General Administration
Purchasing
54.1306-Reroof Building 77,000
54.2505-Fork Lift 11,000
Coup Info Sys
54.2505-Time & Attendance System 32,620
54.2505-Website Redesign & Host 9,000
Total Admin $ 129,620
Public Safety
Administration
54.2201-Ford Taurus 24,000
Service
54.2201-2008 Ford Expedition (5) 145,000
54.2401-Digital Car Cameras (10) 65,000
54.2505-Fingerprinting System 17,000
Ladder Truck Plus Equipment 778,000
Total Public Safety Splost V S 1,029,000
Public Works
Streets
54.2505-950 Loader 152,000
54.2505-Self Propelled Broom 55,000
54.2501-Truck 25,000
54.2501-Crew Cab Trucks 25,000
54.2501-Used Tractor Truck 35,000
Maintenance
54.2101-Work Truck 18,000
Shop
54.1201-Pave Pierce Street Parking Lots 14,000
54.2105-6000 Pound Fork Lift 30,000
Total Public Works S 354,000
Leisure Services
Administration
54.2201-New Vehicle 20,000
Parks & Cemeteries
54.2201-Work Truck 16,000
Programs
54.2201-Vehicle 20,000
Total Leisure Services S 56,000
Utilities
Water & Sewer - Meters
Water & Sewer - Sewage Plant
54.1405-Repave Around Plant 30,000
Water & Sewer - Dist. & Collection
54.2105-Tapping Machine 7,800
54.2201-Pick. Up Truck 25,000
Natural Gas
54.1405-Loop Gas System 45,000
(Commodore Park And Atlanta Concrete)
54.2105-All Terrain Vehicle
54.2201-Pick Up Trucks (2) 20,000
Total Utilities S 127,800
City Wide Capital Outlay For 2008-2009 S 1,723,420
=================================
Recapitulation
General Fund Total S 522,620
Internal Service Fund Total 44,000
Water & Sewer Total 62,800
Gas Total 65,000
Splost V Total 1,029,000
City Wide Capital Outlay For 2008-2009 S 1,723,420